Main Corporate Website
-
XPS
-
Glencore Technology
-
Zipatank
-
Hypersparge
-
IsaKidd
-
IsaMill
-
IsaSmelt
-
JamesonCell
-
Albion Process
-
Viterra
-
Aquarius Energy
-
Glencore in South Africa
-
Glencore in the DRC
-
Mutanda Mining
-
Kamoto Copper Company
-
Astron Energy
-
Katanga Mining Limited
-
Glencore Australia
-
Viterra Australia
-
Bulga Coal
-
Liddell Coal
-
Mangoola
-
McArthur River Mine
-
Mt Owen Complex
-
Ravensworth operations
-
Ulan Coal
-
United Project
-
Wandoan Coal
-
West Wallsend
-
Murrin Murrin
-
Mount Isa Mines
-
Main MenuWho we are
-
Main MenuOperations and projects
-
Operations and projectsCoal
-
Who we are -
CoalCurrent operations
-
Current operationsBulga Coal
-
Current operationsClermont Open Cut
-
Collinsville Open Cut -
Hail Creek Open Cut -
Hunter Valley Operations -
Current operationsIntegra Underground
-
Current operationsLiddell Coal Operations
-
Current operationsMangoola Open Cut
-
Current operationsMt Owen/Glendell Open Cut
-
Newlands Coal -
Oaky Creek Coal -
Current operationsRavensworth Operations
-
Rolleston Open Cut -
Current operationsUlan Coal
-
Current operationsUnited Wambo
-
-
CoalPast operations
-
Past operationsBaal Bone Colliery
-
Bulga Underground -
Past operationsMacquarie Coal
-
Ravensworth Underground
-
-
CoalProjects
-
CoalSustainability
-
CoalMedia
-
MediaNews
-
-
CoalCareers
-
Suppliers -
Contact us
-
-
Operations and projectsQueensland Metals
-
Queensland MetalsWho we are
-
Queensland MetalsOperations
-
Operational changes -
Queensland MetalsSustainability
-
Queensland MetalsMedia
-
Queensland MetalsCareers
-
Suppliers -
Contact us
-
-
Operations and projectsMcArthur River Mine
-
McArthur River MineWho we are
-
McArthur River MineSustainability
-
See our mine site -
McArthur River MineMedia
-
MediaNews
-
-
Careers -
Suppliers -
Contact us
-
-
Operations and projectsMurrin Murrin Operations
-
Murrin Murrin OperationsWho we are
-
Murrin Murrin OperationsSustainability
-
Murrin Murrin OperationsCareers
-
Suppliers -
Murrin Murrin OperationsMedia
-
Contact us
-
-
Operations and projectsAurukun Bauxite Project
-
Aurukun Bauxite ProjectWho we are
-
Aurukun Bauxite ProjectSustainability
-
News and publications -
Suppliers -
Contact us
-
-
CTSCo Project -
Glencore Surat Hydrogen Project -
Glencore Oil
-
-
Main MenuSustainability
-
Main MenuMedia
-
Main MenuCareers
-
Suppliers
Glencore’s Mount Isa Mines Lead Smelter is revisiting a past technique in the blast furnace to help reduce downtime and maximise production capability.
The purpose of the Lead Smelter blast furnace at Mount Isa Mines is to reduce lead oxide into molten lead metal, and to form a low melting point slag (waste) that removes zinc and iron from the lead.
In the 1960s, Mount Isa and Port Pirie lead smelters jointly developed a water-cooled lead spout, made from cast iron, to transport molten lead metal within their blast furnace operations.
Molten lead reaches temperatures between 1,100 and 1,200 degrees Celsius and passes over the lead spout at a rate of around 33 tonnes per hour. These intense conditions make cooling and durability crucial factors in the success of a lead spout.
The jointly developed lead spout worked well for both operations, until the early 1990s when Mount Isa Mines modified the front of their lead smelter blast furnace and increased the size of the forehearth, rendering the existing spout ineffective.
A new precast, refractory lined steel spout known as the block and tile was trialed and eventually adopted as the replacement solution.
Lead Smelter Operations Superintendent, Bill Scotney, says while it did the job, the block and tile arrangement wore quickly and needed frequent replacement.
“We were shutting down the blast furnace every four or five weeks for around 20 hours just to replace the block and tile spout, impacting production,” Bill says.
“Because of this, we trialed a new water cooled lead spout design between 2014 and 2015 with varied success and eventually returned to the block and tile method.”
Determined that it was an issue they could resolve, the Lead Smelter team decided to revisit the water-cooled lead spout again last year.
“We believe that the primary failure in 2014 and 2015 was due to insufficient cooling of the lead spout, which we’ve now been able to fix,” Bill says.
Lead Smelter Senior Project Coordinator, Peter McKellar, was heavily involved in the project trials and in training the operators to ensure its safe and correct operation.
“The project team did a lot of computer modelling to ensure the effectiveness of the solution and to ensure the safety of the operators in the area,” says Peter.
“Not only are the operators finding the new lead spout design much easier to maintain, but we are currently running even better than our modelling specifications.”
“We implemented the new design this year and we’ve successfully maintained the spout at an acceptable temperature.”
“This bodes well for a long-term solution that should see plant availability increased substantially,” Peter says.
With a new cooling arrangement in place, the success of the spout design should allow the blast furnace to push out shutdowns to once every six months − at which time the forehearth will have reached its useful life and require replacement.
General Manager Smelting and Refining, Adrian Herbert, praised the various functional areas on working together to achieve better operating conditions.
“Continuous improvement initiatives such as this one require input and commitment from a broad cross-section of functions, including engineering, maintenance, operations and safety,” says Adrian.
“The redesigned water cooled lead spout solution is proving very effective and we are already seeing the benefits on plant availability and lead bullion production.”
“This is just one of many improvement projects we have been working on across the entire Queensland Metals Smelting and Refining department,” Adrian says.