George Fisher Mine welcomes its newest fans

Success is a breath of fresh air for the team who recently completed a major ventilation project at our George Fisher Underground Mine.

The significant infrastructure project took many months of planning and involved drilling two new 3.5 metre diameter shafts − a fresh air intake and a return air shaft – from the surface 335 metres underground to provide an additional ventilation capacity at GFM.

Ventilation is a critical control in our underground mines with fresh air constantly being circulated throughout the mine to ensure we keep our people safe.

This project was needed to provide additional ventilation capacity and will allow for the safe extraction of a mining block affectionately known as 'the blob' due to the unique shape of the orebody.

Senior Project Engineer at George Fisher Mine, Robert Harrington, says the project wasn't without its challenges and along the way some innovative engineering solutions needed to be developed.

"We encountered around 15 metres of ground that wasn't self-supporting on the return air shaft so we came up with the idea to use a secant pile wall to stabilise and support the ground," says Rob.

  • The use of a secant pile wall to stabilise and support the ground.
  • The fan from above providing an aerial perspective.

"In 10 days we installed 18 concrete piles down 15 metres which used 450 cubic metres of concrete. The pile wall was capped with a 100 square metre slab to support the raise borer."

"I believe this was the first time this civil engineering technique has been used in Mount Isa," Rob says.

"All up the civil works for the fan installation involved the pouring of over 1,000 cubic metres of structural concrete."

  • The fan from above providing an aerial perspective.
  • Mine ventilation - I'm a huge fan!

The two shafts were drilled using conventional raise boring. This is a mining technique whereby a small pilot hole is drilled down into a void or chamber underground and then a large diameter reamer is attached which opens the shaft to its final diameter by cutting as it is lifted back to the top of the hole.

Rob says raise boring is an efficient way to create vertical openings with the two 335 metre deep shafts installed in less than four months.

"Reaming rates achieved through softer ground near the surface were fantastic and we achieved a maximum reaming rate of 31 metres in a 24 hour period which is quite amazing," says Rob.

Once completed, the two shafts were lined with remotely sprayed shotcrete to ensure they remain stable for the life of the mine.

Installation and commissioning of the electrical works and the fan took 6 weeks to complete and the fan was commissioned in March 2020.

"The fan structure is quite massive. With a 4.5 metre diameter impeller and total height of 17 metres the fan pumps over 200 cubic metres of air per second," Rob says.

The impeller on the fan is 4.5 metres in diameter and can pump 200 cubic metres of air per second.

"The ducting for the fan was manufactured in Vietnam, the impeller was manufactured in Melbourne, the motor and variable speed drive came from Germany with the majority of the installation undertaken by local labour."

One of the major challenges in successfully delivering the project Rob says was the integration of five major contracts which ran concurrently.

"We had to bring together and manage the project across five disciplines − mechanical, electrical, civil, raise boring and shaft lining."

"Managing the interface between the different disciplines was critical to ensuring we delivered the project safely and in accordance with the baseline schedule."

"It was a great collaborative effort and I'm really proud of the team as it was a huge effort over the nine months of the project."